Major concrete placement completed for Vogtle Unit 4
21-hour continuous placement inside nuclear island precedes setting of reactor vessel

ATLANTA, Dec. 22, 2017 /PRNewswire/ -- Significant progress continued this week at the Vogtle nuclear expansion site near Waynesboro, Georgia with the placement of nearly 1,300 cubic yards of concrete inside the Unit 4 containment vessel. The continuous placement lasted 21 hours, and involved more than 100 workers and more than 120 truckloads of concrete.

The placement occurred in three main locations - inside the reactor vessel cavity, in the refueling area and on the east side of the containment vessel. This milestone supports the placement of the reactor vessel early next year and advances progress on the east side of containment.

In 2017, more than 57,000 cubic yards of concrete have been placed for the Vogtle project, bringing the project's total to approximately 545,000 cubic yards, enough concrete to build a sidewalk from Miami to Seattle.

The new units at Plant Vogtle (co-owned by Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities) are the only new nuclear units currently under construction in the United States and, once complete, will generate enough electricity to power approximately 500,000 homes and businesses.  To follow the progress, the Georgia Power YouTube Channel and view new photos added each month in the Plant Vogtle 3 & 4 Online Photo Gallery.

Georgia Power to move forward with Vogtle 3 & 4
Georgia Power announced on Dec. 21 that it will move forward with the Vogtle 3 & 4 project following unanimous approval by the Georgia Public Service Commission (PSC).

The decision by the Georgia PSC followed months of review and evaluation of a unified recommendation presented on August 31 by the Vogtle co-owners. The recommendation was based on the results of a comprehensive schedule, cost-to-complete and cancellation assessment that was prompted by the bankruptcy of former primary Vogtle contractor Westinghouse in March and the subsequent rejection of the fixed-price contract. The decision continues to protect customers with new penalties for delays and cost increases in addition to penalties included in the previous stipulated agreement approved earlier this year by the Georgia PSC. Under this amended structure, shareholders will see a significant impact of approximately $750 million through November 2022 and the company has agreed to further reductions if the project does not meet the revised and approved in-service dates. Additionally, as a result, the amount paid by customers will be reduced by more than $1.7 billion during the construction period.

From the beginning of the Vogtle expansion, Georgia Power has worked to pursue all available benefits for customers and minimize the impact of the new units on electric bills. In September, the company announced a new conditional commitment of approximately $1.67 billion in additional loan guarantees for the project from the U.S. Department of Energy (DOE) illustrating renewed federal support for the project. Most recently, the company received 100 percent of parent guarantee funds available from Toshiba years earlier than expected and will use every dollar to benefit customers. The parent guarantee payments from Toshiba, in addition to the penalties in place for the company, are contributing approximately $2.75 billion which will reduce the total cost of the project.

Final approval and issuance of the additional loan guarantees by the DOE cannot be assured and are subject to the negotiation of definitive agreements, completion of due diligence by the DOE, receipt of any necessary regulatory approvals, and satisfaction of other conditions.

Read more about the decision to complete Vogtle 3 & 4 here.

About Georgia Power
Georgia Power is the largest electric subsidiary of Southern Company (NYSE: SO), America's premier energy company. Value, Reliability, Customer Service and Stewardship are the cornerstones of the company's promise to 2.5 million customers in all but four of Georgia's 159 counties. Committed to delivering clean, safe, reliable and affordable energy at rates below the national average, Georgia Power maintains a diverse, innovative generation mix that includes nuclear, coal and natural gas, as well as renewables such as solar, hydroelectric and wind. Georgia Power focuses on delivering world-class service to its customers every day and the company is consistently recognized by J.D. Power and Associates as an industry leader in customer satisfaction. For more information, visit www.GeorgiaPower.com and connect with the company on Facebook (Facebook.com/GeorgiaPower), Twitter (Twitter.com/GeorgiaPower) and Instagram (Instagram.com/ga_power).

Cautionary Note Regarding Forward-Looking Statements
Certain information contained in this communication is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning additional DOE loan guarantees and other future actions related to Plant Vogtle Units 3 and 4. Georgia Power cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of Georgia Power; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Georgia Power's Annual Report on Form 10-K for the year ended December 31, 2016, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: the impact of any failure to extend the in-service deadline for federal production tax credits; the impact of any failure to amend the DOE loan guarantee to allow for additional borrowings; state and federal rate regulations and the impact of pending and future rate cases and negotiations; the impact of recent and future federal and state regulatory changes, as well as changes in application of existing laws and regulations; current and future litigation, regulatory investigations, proceedings, or inquiries; available sources and costs of fuels; effects of inflation; the ability to control costs and avoid cost overruns during the development construction and operation of facilities, which include the development and construction of generating facilities with designs that have not been finalized or previously constructed; the ability to construct facilities in accordance with the requirements of permits and licenses, to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; advances in technology; legal proceedings and regulatory approvals and actions related to Plant Vogtle Units 3 and 4, including Georgia Public Service Commission approvals and Nuclear Regulatory Commission actions; interest rate fluctuations and financial market conditions and the results of financing efforts; changes in The Southern Company's or Georgia Power's credit ratings, including impacts on interest rates, access to capital markets, and collateral requirements; the impacts of any sovereign financial issues, including impacts on interest rates, access to capital markets, impacts on foreign currency exchange rates, counterparty performance, and the economy in general, as well as potential impacts on the benefits of DOE loan guarantees; and the effect of accounting pronouncements issued periodically by standard setting bodies. Georgia Power expressly disclaims any obligation to update any forward-looking information.

Georgia Power logo. (PRNewsFoto/Georgia Power)

SOURCE Georgia Power

For further information: Georgia Power Media Relations, (404) 506-7676 or (800) 282-1696, www.georgiapower.com