Power restoration estimates announced
Gulf Power crews began restoration work in ernest on Friday in the Panama City area.

Crews have restored power to more than 40,000 Gulf Power customers in the wake of Hurricane Michael, and estimated restoration times have now been assigned for some of the areas significantly impacted by Hurricane Michael.

“We’re committed to getting the entire community up and running as soon as possible,” said Jeff Rogers, Gulf Power spokesperson. “It’s important for our customers to understand that it’s going to take longer in some areas to rebuild our electrical system — some of our major line infrastructure is located in heavily wooded areas or is difficult to access.”

Estimated Restoration Times

Customers in the hardest hit areas should prepare to be without power for weeks. The following estimated restoration times are for 95% of customers who are able to be take service.

  • Bay County west of Highway 79 is estimated to be restored by midnight, Oct. 14.

  • Bay County east of Highway 79 to the Hathaway Bridge is estimated to be restored by midnight, Oct. 15.

  • Holmes, Jackson and Washington counties are estimated to be restored by midnight, Oct. 19.

  • Gulf Power is still working to determine restoration estimates in the hardest hit areas including downtown Panama City, Callaway, Parker, Lynn Haven, Youngstown and surrounding areas.

“We ask for patience and understanding over the coming days and weeks,” said Rogers. “Crews will be working 24 hours a day, seven days a week until every last customer has power. More storm restoration crews have been secured, bringing the total to more than 5,800 storm personnel working to restore power.”

Current storm-related outage total as of 5 p.m. CDT

 

County

Outages

 

Customers Served

Bay

92,857

 

103,367

Escambia

RESTORED

 

152,984

Holmes

2,100

 

2,572

Jackson

1,206

 

1,375

Okaloosa

RESTORED

 

94,172

Santa Rosa

RESTORED

 

72,563

Walton

3,465

 

23,578

Washington

6,493

 

6,514

TOTAL

 

 

457,125

Restoration process
 

Watch How Power is Restored

Gulf Power’s process following the storm begins with evaluation teams arriving in smaller trucks that can more easily navigate through debris and damage. Those teams are still working to determine the damage to the Gulf Power grid in Panama City, but many roads still must be cleared and made safe before more crews can get their larger bucket trucks in to begin the restoration and rebuilding process.

Issues like trees and heavy debris blocking roads, and communications down can slow down the rebuilding and restoration process, but Gulf Power is prepared for this type of storm devastation. 

As roads are being made safe, and with a restoration plan is in place, crews are beginning the restoration and rebuilding process. This process begins with transmission lines, which are the larger lines on the taller poles that bring power from Gulf Power’s generating plants to the substations.

Transmission lines are being inspected and repaired and substation crews are inspecting and repairing substations. Substations step down the voltage of the electricity from the power plants to a level that powers homes and businesses.

While any repairs are being made to the substations, crews will be inspecting the distribution lines and beginning the restoration process replacing poles, lines, transformers and more. Distribution lines carry electricity from our substations to homes and businesses.

Safety Tips

Gulf Power urges our customers to ensure that safety is a top priority. With extensive damage to critical infrastructure, it is important to keep safety tips at the forefront.