Estimated restoration times announced for all customers
Gulf Power announces that by midnight, Oct. 24, fourteen days after landfall of Hurricane Michael, 95 percent of all Gulf Power customers who can accept electric service should be restored.
Gulf Power announces that by midnight, Oct. 24, fourteen days after landfall of Hurricane Michael, 95 percent of all Gulf Power customers who can accept electric service should be restored. Customers in several areas will be restored sooner. Over the last 24 hours, more than 21,000 Gulf Power customers have been restored.
“Hurricane Michael was an unprecedented storm, and Gulf Power is on a mission to ensure an unprecedented response.” said Stan Connally, Chairman, president and CEO of Gulf Power. “We know that our customers are counting on us, so they can begin rebuilding their lives. We are working safely and aggressively around the clock to get the lights back on.”
Estimated Restoration Times – View map for a visual of estimated restoration times
o Areas north of I-10 in Bonifay and Chipley, and all of Caryville and Campbellton are estimated to be restored by midnight, Oct. 17. o Vernon, Sunny Hills and the surrounding areas south of I-10 are estimated to be restored by midnight, Oct. 18. o Customers who live in the Cypress and Apalachee areas with a mailing address of Sneads, Florida, served by Gulf Power, are estimated to be restored by midnight, Oct. 19
*The above estimated restoration times are for 95% of customers who are able to take service. As work progresses, we will continue to update and adjust estimated restoration times for specific areas.
Current storm-related outage total as of 11 a.m. CDT
|